How We Build: The Modular Construction Process from Brief to Handover
The modular construction process here runs in six stages: your brief, a scheme against your plot, drawings, the quotation, manufacture, and assembly on your ground. Each settles something before the next starts.
Questions
Questions to settle around a release-led path from brief to handover.
How long does the whole thing take, honestly?
Longer than the number this market advertises, because that number covers assembly and nothing else. Sixty to ninety days on site is the manufacturing group’s record. Ahead of it lie every stage above: the first conversation, the scheme, the sheets, the approvals you have to obtain and the making of the components. Your realistic total arrives with the quotation.
What do I have to do before delivery day?
Three things, all named back to you at the scheme stage: a road a loaded flat-bed can use, a clear working area alongside the footprint, and a finished base with the services already run to it. They are the only items on the programme that are not ours, which is why they are written down as early as they are.
Can I stop after the drawings?
Yes. The set is issued to be read and judged, by your own architect if you would rather not judge it yourself, and there is nothing further to sign before that happens. A reader who gets to the end of the sheets and decides against the building has learned something worth knowing, which is what issuing them is for.
Do you build it, or do I appoint a contractor?
The components are manufactured and delivered, and the assembly is carried out to the drawn sequence. What sits outside that scope — foundations, the ground under them, services beyond the boundary and anything a licensed signature is required for — is set out in the quotation and handled by the consultants you appoint for it.
What happens if the design has to change once work starts?
The intention is that it does not, which is what the scheme stage on your own survey exists to prevent. Where a change is unavoidable, it is drawn first and priced against the drawing, and the sheets are reissued with a revision letter. A change agreed verbally on site is the most expensive kind, and it is not how this works.
What am I given at handover?
The building, the design set at its final revision, the finishes and openings schedules, and the terms of the twenty-five-year warranty as they apply to your project. That warranty is the manufacturing group’s, qualified per building, and it does not reach structural design, foundations, services or any figure of performance.
Start at the plot, not the picture
Send the location, the approach road and what the building is for, and the first conversation will be about your ground rather than about our designs.